Well, this process is taking longer than I expected, but I guess that's always the way. A few really nice folks came out Friday and did more conduit installation and wired things into the main breaker panel. They also started to do some work on the roof.
We had a freak lightning storm this morning and had a little rain, I was nervous since the inverter is still open on the bottom, and I didn't know what condition the roof was in, but hopefully it wasn't enough to be overly concerned about.
They came again today for about 4 hours, dropped off the 24 panels (WOW, they're a *lot* bigger than I expected - see new photos).
I managed to get some pictures of the roof and how the installation is going. Have a new gallery being hosted over at the good folks at SmugMug, check out the photos here:
Hopefully tomorrow I'll have more to update and have some pictures of some panels on the roof!